TotalEnergies announces the restart of production from the Tyra hub in the Danish North Sea, after the completion of a major redevelopment project of this hub. At plateau, the Tyra hub will produce 5.7 million cubic meters of gas and 22,000 barrels of condensate per day, once again making Denmark self-sufficient and a net exporter of natural gas. TotalEnergies operates the Tyra field on behalf of Danish Underground Consortium, a partnership between TotalEnergies (43.2%), BlueNord (36.8%) and Nordsøfonden (20%).
“We are pleased to restart the Tyra hub, one of the most technologically advanced offshore gas installations in the world. The success of this major redevelopment project owes a lot to the commitment of our teams, our partners and our contractors. The new Tyra leverages state-of-the-art digital solutions and technological innovations to produce more efficiently and with 30% lower greenhouse gas emissions than the former facilities”, said Nicolas Terraz President, Exploration & Production at TotalEnergies. “Importantly, the resumption of gas production from Tyra improves Europe’s security of supply.”
Discovered in 1968 by Maersk Oil, Tyra is located 225 kilometres west of the coast of Esbjerg. In September 2019, gas production was suspended to enable the redevelopment of Tyra. Following the decommissioning of the previous Tyra facilities, 8 new platform topsides, 2 jackets and 6 bridges were installed. As part of this redevelopment project, 98.5% of the materials recovered from the retired installations have been reused or recycled.
by Fuel Type (Diesel, Gas, LPG, Biofuels), Power Rating (Up to 50 kW 51-280 kW, 281-500 kW, 501-2000 kW, 2001-3500 kW, Above 3500 kW), Application, End-User Industry, Design, Sales Channel, Region
Download free sample pagesGas from the Tyra hub is delivered to Europe through two export pipelines to Nybro in Denmark and Den Helder in the Netherlands.