Georgia Power Receives First Nuclear Fuel Shipment for Vogtl
Stay informed with our
free newsletters

This news is classified in: Traditional Energy Nuclear

Dec 9, 2020

Georgia Power Receives First Nuclear Fuel Shipment for Vogtle Unit 3

  • Represents the first nuclear fuel delivery for the newly-designed reactor in the U.S.
  • Signifies a major step for the nuclear expansion project towards operations
  • Unit 3 construction is now approximately 96% complete

Georgia Power has received the first nuclear fuel shipment for Vogtle Unit 3, representing the first nuclear fuel shipment for this newly-designed AP1000 reactor in the U.S. The milestone marks a major step for the Vogtle 3 & 4 nuclear expansion project towards operations and providing customers with a carbon-free energy source that is expected to put downward pressure on rates for decades to come.

"Since the start, the Vogtle expansion project has been an investment in our energy future. Today, as we receive our first nuclear fuel shipment, we remain committed to realizing the benefits this project will provide not only to our customers, but also our state and our country," said Paul Bowers, chairman and CEO of Georgia Power. "Achieving this historic milestone brings us closer to fuel load expected in April 2021, and, once online, these new nuclear units will provide clean, carbon-free energy for the next 60 to 80 years."

In order to receive nuclear fuel, construction of specific areas of Unit 3 had to be completed and inspected, ensuring critical infrastructure, such as the fuel vault and spent fuel pool, meet construction quality and design requirements. With site construction turning over the fuel handling area of Vogtle Unit 3 to operations, the Vogtle 3 & 4 site implemented specific and comprehensive policies, procedures and security measures to safely receive, handle and store the nuclear fuel.

Small Modular Reactor Market for Data Centers - Analysis and Forecast, 2028-2033

Small Modular Reactor Market for Data Centers - Analysis and Forecast, 2028-2033

A Global and Regional Analysis: Focus on Product, Application, and Country

Download free sample pages

With the receipt of the first nuclear fuel assemblies, the Vogtle 3 & 4 project remains focused on one of the last major milestones ahead for Unit 3, hot functional testing. This series of tests is the last critical step before fuel load and ultimately in-service operation.

Carbon-free energy source
The new Vogtle units are an essential part of Georgia Power's commitment to deliver safe, clean, reliable and affordable energy for customers and play a significant role in supporting Southern Company's goal of net-zero carbon emissions by 2050.

Once operating, the two new units at Plant Vogtle will be able to power more than 500,000 homes and businesses. A diverse fuel mix, including nuclear, is also essential to maintaining a reliable and affordable energy infrastructure that attracts new investment, supports economic growth and creates jobs.

Nuclear fuel process
One nuclear fuel pellet, roughly the size of a pencil eraser, provides as much energy as one ton of coal or nearly 150 gallons of oil. The nuclear fuel pellets are enclosed in nuclear fuel rods, which are then part of nuclear fuel assemblies. Consisting of 157 fuel assemblies with each measuring 14 feet tall, the fuel will be loaded into the reactor vessel to support startup once the reactor begins operating. After the initial fueling, approximately one third of the total fuel assemblies will be replaced during each refueling outage after the units begin operating, similar to the process used at existing Vogtle Units 1 & 2.

Earlier this year, the Vogtle 3 & 4 project team successfully completed the pre-startup review process conducted by the World Association of Nuclear Operators (WANO), which assessed the Vogtle 3 & 4 nuclear expansion project's readiness to operate the new AP1000 reactors with safety and quality as the primary focus.


Georgia Power