Vestas has received a 45 MW order in Türkiye. The contract includes the supply and installation of 10 V150-4.5 MW wind turbines as well as a 15-year Active Output Management 4000 (AOM 4000) service agreement.
“We believe that the reliability and versatility of our portfolio will continue to play a paramount role in Türkiye’s energy transition”, says Vestas Head of Türkiye, Levent Ishak.
Turbine delivery is scheduled for the first half of 2025, while commissioning is expected to take place in the second half of 2025.
Key data points: The growth forecast = 7.0% annually for the next 7 years. Scroll below to get more insights. This market report covers trends, opportunities, and forecasts in CF Textile in the global wind energy market to 2031 by product type (woven textiles and non-woven textiles), application (blades and others), and region (North America, Europe, Asia Pacific, and the Rest of the World)
Download free sample pagesVestas installed Türkiye’s first wind turbine in 1984 and has since then delivered over 2 GW of wind capacity in the country.